Which documents do you need at each stage?
List each required document, its due date and who will review it on the purchase order. Flag any drawing approval or inspection sign-off that must happen before work proceeds.
| When | Documents to check | What to verify |
|---|---|---|
| Before purchase | Pipe data sheet, fitting drawings and any required product approvals | The quoted pipe and fittings match the line schedule and equipment connections. |
| Before production | Approved drawing revisions and the inspection and test plan (ITP), if required | The factory and project inspector agree on tests, acceptance criteria and witness dates. |
| Before dispatch | Factory inspection report, packing list and any agreed release documents | The shipment can be matched to the inspection records and approved order. |
| At the mine | Receiving record, joining instructions and equipment manuals | The crew can identify each delivery lot and find the documents needed for installation and handover. |
Check drawings and approvals before ordering
- Pipe data sheet. Match the material grade, product standard, actual outside diameter (OD), metric or IPS series, SDR or DR, and pressure rating to the line schedule.
- Fitting and spool drawings. Confirm the drawing revision, end dimensions and face-to-face length. For a pump or valve tie-in, verify the backing-ring drilling against the mating flange drawing. Review the flange interface checklist for the dimensions to send.
- Product approvals. Where the specification calls for an approval, check that the current document covers the offered product, size range and intended service. Review Puhui’s product approval scopes.
Agree on inspection and shipment release
Puhui supplies a factory inspection report and packing list with the shipment. If your project requires a resin Certificate of Analysis (COA), a signed conformity declaration or third-party inspection, include those requirements at quotation so they can be scheduled.
Before production, use the inspection and test plan to agree on tests, sampling, acceptance criteria, witness points and who signs off for dispatch. Before release, check that the report identifies the pipe specification and production lot. Agree how bundle, pallet or carton IDs will appear on the packing list.
See Puhui’s factory checks and batch records · Review export packing
Match delivered items to the inspection records
- Use the packing list to count pipes, fittings and accessories against the purchase order. Record shortages, damaged packaging or damaged pipe ends at receiving.
- Check the pipe markings and fitting labels against the approved line items. Use the production lot on the pipe marking, or the agreed packing-list cross-reference, to find the corresponding inspection report. Hold any item with an unreadable mark or a mismatched record for review.
- Keep the receiving record, applicable joining procedures and equipment manuals with the handover file. Add the crew’s weld logs and field test records where the project requires them.
Use the pipe receiving and storage guide for condition checks before installation.
Request a pipe and fittings quote with a document list
Send your pipe and fitting schedule, quantities, drawing revisions, required approvals and delivery location. Include any inspection or witness dates and document deadlines. Puhui can quote the pipe, matching fittings and flange assemblies together and confirm which documents are included with the offer or shipment.